2026-05-03 · Project Manager
| v1.0.0 (CERRADO) | v2.0.0 (INICIO) |
|---|---|
| Motor IT ops específico | Motor genérico multi-dominio |
| 1 dominio fijo | Perfiles de dominio configurables |
| API v1 (español) | API v2 (English-Only) |
| Single-tenant lógico | Scoping multi-tenant |
| MVP funcional (v1) | MVP completo (v2) |
Decisión del sponsor: v1 descartado, sin backward compat.
Abax-Memory v2 es un motor de memoria aumentada con IA para cualquier profesional, en cualquier dominio.
| Métrica | Valor |
|---|---|
| Épicas | 10 |
| Features | 85+ |
| Historias de Usuario | 69 |
| MVP (Must) | 66 |
| Post-MVP | 3 |
R1 Core: 43 historias | R2 Completo: 23 historias
| Rol | Responsable |
|---|---|
| Project Manager | @project-manager |
| Business Analyst | @business-analyst |
| Solution Architect | @solution-architect |
| Tech Lead | @tech-lead |
| Backend Dev | @developer-backend |
| Frontend Dev | @developer-frontend |
| QA Functional | @qa-functional |
| DevOps | @devops |
Metodología: Cascada con releases incrementales (R1 + R2)
Modelo: Ligero (Lightweight)
| Fase | Inicio | Fin | Duración |
|---|---|---|---|
| F1 Inicio | 04-May | 07-May | 3 días |
| F2 Análisis | 08-May | 28-May | 3 sem |
| F3 Diseño | 29-May | 19-Jun | 3 sem |
| F4 Construcción | 20-Jun | 20-Nov | 22 sem |
| F5 QA | 21-Nov | 18-Dic | 4 sem |
| F6 UAT | 19-Dic | 22-Ene | 5 sem |
| F7 Despliegue | 23-Ene | 29-Ene | 1 sem |
| F8 Estabilización | 30-Ene | 19-Feb | 3 sem |
| F9 Cierre | 20-Feb | 26-Feb | 1 sem |
| Hito | Fecha | Criterio |
|---|---|---|
| M1 Kickoff | 04-May | Acta firmada |
| M2 Design Gate | 19-Jun | Arquitectura aprobada |
| M3 Gate R1 | 18-Sep | R1 Core verificado |
| M4 Build Complete | 20-Nov | MVP construido |
| M5 QA Gate | 18-Dic | 0 críticos abiertos |
| M6 UAT Sign-off | 22-Ene | Sponsor aprueba |
| M7 Go-Live | 29-Ene | En producción |
| M8 Cierre | 26-Feb | Lecciones aprendidas |
| # | Riesgo | Score |
|---|---|---|
| R-008 | Perfiles de dominio insuficientes | 12 |
| R-001 | Stack flexible sin ADR | 12 |
| R-002 | English-Only adoption friction | 12 |
| R-014 | Presión de cronograma | 10 |
| R-011 | Fallo en benchmarks (BEIR) | 10 |
17 riesgos totales. Revisión semanal + por gate.
Go-Live objetivo: 29 de Enero 2027
Hemos revisado la visión, el alcance, el equipo, el cronograma y los riesgos principales del proyecto Abax-Memory v2.0.0.